Timeline for Conservation Landscaping at Derwood Station 2

Start Date: 02/01/2017  

End Date: 03/01/2017

Develop final design and planting plan based on prior Trust feedback. Submit to Trust for approval and hold pre-construction and pre-planting meeting with HOA, designer and Trust staff; review other construction details

Start Date:  03/01/2017

End Date:  03/07/2017

 

Develop RFQ for installation and put out to bid to contractor. Review and select installation contractor and schedule contractor as well as volunteer events with the HOA.

 

Start Date:  04/01/2017

End Date:  06/01/2017

 

Installation of landscaping. RCC and HOA to conduct volunteer activity as part of installation

 

Start Date:  05/01/2017 End Date:  06/01/2017

 

Post-construction meeting with HOA, designer, and contractor to ensure practice was implemented

as designed, to address any final comments, and to receive post-

construction approval

 

Start Date:  06/01/2017

End Date:  07/01/2017

 

RCC and HOA to develop signage verbiage and graphics, contract for manufacture of signage. Install signage.

 

Start Date:  06/15/2017

End Date:  06/30/2017

 

RCC to conduct community outreach activity mid-summer 2017. Train select HOA board members by RCC to serve as ambassadors for the project.

 

Start Date:  05/01/2018

End Date:  02/01/2019

 

Maintenance including weeding, invasive plants monitoring, deer browse spraying, and watering on a monthly schedule.

 

Start Date:  05/01/2018

End Date:  02/01/2019

 

Evaluation of project success, visits during and after major rain events as needed through project completion.