Timeline for Conservation Landscaping at
Derwood Station 2 |
|
Start Date: 02/01/2017 End Date: 03/01/2017 |
Develop final design and planting plan based on prior Trust feedback. Submit to Trust for approval and hold pre-construction and pre-planting meeting with HOA, designer and Trust staff; review other construction details |
End Date: 03/07/2017 |
Develop RFQ for installation and put out to bid to contractor. Review and select installation contractor and schedule contractor as well as volunteer events with the HOA. |
Start Date: 04/01/2017 End Date: 06/01/2017 |
Installation of landscaping. RCC and HOA to conduct volunteer activity as part of installation |
Start Date: 05/01/2017 End Date: 06/01/2017 |
Post-construction meeting with HOA, designer, and contractor to ensure practice was implemented as designed, to address any final comments, and to receive post- construction approval |
Start Date: 06/01/2017 End Date: 07/01/2017 |
RCC and HOA to develop signage verbiage and graphics, contract for manufacture of signage. Install signage. |
Start Date: 06/15/2017 End Date: 06/30/2017 |
RCC to conduct community outreach activity mid-summer 2017. Train select HOA board members by RCC to serve as ambassadors for the project. |
Start Date: 05/01/2018 End Date: 02/01/2019 |
Maintenance including weeding, invasive plants monitoring, deer browse spraying, and watering on a monthly schedule. |
Start Date: 05/01/2018 End Date: 02/01/2019 |
Evaluation of project success, visits during and after major rain events as needed through project completion. |